Standard Operating Procedure for Strip Packaging Machine in Ocular Dosage Form Manufacturing
1) Purpose
The purpose of this SOP is to establish a standardized procedure for the operation, cleaning, and maintenance of the strip packaging machine to ensure proper packaging of ocular dosage forms.
2) Scope
This SOP applies to all strip packaging machines used in the manufacturing of ocular dosage forms within the pharmaceutical manufacturing facility.
3) Responsibilities
Production personnel are responsible for operating the strip packaging machine and ensuring that ocular dosage forms are packaged securely and correctly. Quality control personnel are responsible for verifying the integrity of packaged products and compliance with SOPs.
4) Procedure
4.1 Preparation for Strip Packaging
- Ensure the strip packaging area is clean, organized, and free from contaminants.
- Verify the availability and condition of all packaging materials, such as strip packs and foils.
- Set up the strip packaging machine according to the product specifications and batch records.
- Record the batch number, product name, and quantity of units to be packaged in the batch production log.
4.2 Strip Packaging Process
- Preparation of Strip Packaging Equipment
- Calibrate the strip packaging machine to ensure proper settings (temperature, sealing pressure, etc.).
- Load the strip packs and fill them with ocular dosage forms according to the batch record instructions.
- Sealing and
- Initiate the strip packaging process and monitor the machine for proper operation.
- Verify each sealed strip pack for completeness and security.
- Take samples of packaged units for quality control testing, including visual inspection and packaging integrity.
- Record the results of quality control tests in the batch production log.
- If any units fail quality control tests, investigate and take corrective actions before proceeding.
- Remove the packaged units from the strip packaging machine and inspect them for any defects or abnormalities.
- Label the packaged units with the batch number, product name, and expiry date.
- Transfer the packaged units to the designated storage area under controlled conditions.
4.3 Cleaning and Maintenance
- Clean the strip packaging machine and all associated equipment thoroughly after each batch according to the cleaning SOP.
- Perform routine maintenance checks and ensure all parts are properly maintained and calibrated.
- Document all cleaning and maintenance activities in the equipment logbook.
4.4 Documentation
- Record the details of the strip packaging process, including settings, in-process checks, and quality control results, in the batch production log.
- Ensure all records are signed and dated by the personnel responsible for the packaging operation.
- Attach a copy of the batch production log to the batch production record for traceability.
4.5 Review and Approval
- The quality assurance department should review packaging procedures and records periodically to ensure compliance with SOPs and regulatory requirements.
- Any discrepancies or deviations should be investigated, documented, and resolved promptly.
- Review and update the SOP as necessary to reflect changes in procedures, regulations, or industry standards.
5) Abbreviations, if any
SOP: Standard Operating Procedure
QC: Quality Control
6) Documents, if any
- Batch production log
- Batch production record
- Equipment logbook
7) Reference, if any
GMP Guidelines for Pharmaceutical Manufacturing
8) SOP Version
Version 1.0