Standard Operating Procedure for Installation Qualification (IQ) of Capsule Filling Machines
Department | Capsule Manufacturing |
---|---|
SOP No. | SOP/CM/166/2025 |
Supersedes | SOP/CM/166/2022 |
Page No. | Page 1 of 9 |
Issue Date | 01/02/2025 |
Effective Date | 05/02/2025 |
Review Date | 01/02/2026 |
1. Purpose
The purpose of this SOP is to outline the Installation Qualification (IQ) process for capsule filling machines. IQ is an essential step in the validation of new or modified equipment to ensure that it is installed correctly, meets design specifications, and is suitable for use in capsule production. This SOP ensures compliance with GMP and regulatory standards and provides a systematic approach to documenting the IQ process.
2. Scope
This SOP applies to the Installation Qualification (IQ) of all capsule filling machines used in the manufacturing process. It covers the installation procedures, checks, and documentation necessary to validate that the equipment is installed in compliance with design specifications and operational requirements.
3. Responsibilities
- Engineering Team: Responsible for installing the capsule filling machine and ensuring that it meets all installation specifications. The team is also responsible for performing all the installation checks outlined in this SOP.
- Quality Control (QC) Team: Responsible for verifying and documenting the results of the IQ process, including inspecting the equipment for compliance with the specifications and performing functional checks.
- Quality Assurance (QA) Team: Responsible for reviewing and approving the IQ documentation to ensure compliance with GMP and regulatory requirements.
- Production Team: Responsible for ensuring the equipment is properly integrated into the production environment and is ready for use after successful completion of the IQ process.
4. Accountability
The Engineering Supervisor is responsible for ensuring the installation of the capsule filling machine according to the design specifications. The QA Manager is responsible for reviewing and approving the IQ documentation to ensure compliance with GMP and regulatory standards. The Production Supervisor is responsible for ensuring the equipment is ready for use after successful IQ completion.
5. Procedure
5.1 Pre-Installation Setup
Before starting the installation of the capsule filling machine, ensure the following preparations are completed:
-
Review Installation Plan
- Review the installation plan provided by the manufacturer, which should include equipment specifications, installation requirements, and validation protocols.
-
Prepare Installation Environment
- Ensure the installation environment meets the required specifications for the capsule filling machine, including space, electrical connections, and environmental conditions such as temperature and humidity.
- Verify that the installation area is clean, well-lit, and free of any obstructions.
-
Calibrate and Verify Tools
- Ensure all tools and calibration equipment required for installation are verified and calibrated before use. Record calibration details in the Equipment Calibration Log (Annexure 1).
5.2 Installation of Capsule Filling Machine
Follow these steps to install the capsule filling machine:
-
Unpack and Inspect Equipment
- Carefully unpack the capsule filling machine and verify that all parts are present according to the manufacturer’s packing list. Inspect the equipment for any visible damage during shipping.
-
Assemble the Machine
- Assemble the machine according to the manufacturer’s instructions. Ensure all components are securely fastened, and all connections are properly made.
-
Electrical and Mechanical Connections
- Connect the machine to the appropriate electrical supply, ensuring all safety protocols are followed during installation. Check all mechanical connections, such as drive motors, belts, and gears, for proper alignment.
5.3 Installation Checks and Verification
Perform the following checks to ensure the capsule filling machine is installed correctly:
-
Verify Electrical and Mechanical Functionality
- Test the electrical connections to ensure that the machine powers on without any faults. Verify that all mechanical systems, including the filling mechanism, motor, and controls, function correctly.
-
Verify Equipment Alignment
- Ensure that all parts of the machine, including the capsule loading mechanism, filling station, and sealing system, are correctly aligned and calibrated according to the manufacturer’s specifications.
-
Verify Machine Performance
- Perform a test run of the machine without capsules to verify the operation of the filling process and ensure that all components operate smoothly. Record the results in the Installation Qualification Log (Annexure 2).
-
Document Installation Results
- Document the results of the installation checks, including any issues encountered and corrective actions taken, in the Installation Qualification Report (Annexure 3).
5.4 Post-Installation Activities
After successful installation, perform the following tasks:
-
Verify Equipment Readiness
- Verify that all machine settings are correct and that the machine is ready for operation. Ensure that all safety checks, such as emergency stops and guard positions, are in place.
-
Provide Operator Training
- Train the operators on the proper use of the capsule filling machine, including safety protocols, machine settings, and basic troubleshooting procedures.
-
Sign-Off and Approval
- Ensure that the installation qualification process is completed to satisfaction, and the machine is signed off by the QA Manager for use in production. The Installation Qualification Report should be approved and filed for record-keeping.
6. Abbreviations
- SOP: Standard Operating Procedure
- GMP: Good Manufacturing Practice
- IQ: Installation Qualification
- QA: Quality Assurance
- QC: Quality Control
- PPE: Personal Protective Equipment
7. Documents
- Annexure 1: Equipment Calibration Log
- Annexure 2: Installation Qualification Log
- Annexure 3: Installation Qualification Report
8. References
- FDA Guidelines on Equipment Installation Qualification
- Good Manufacturing Practice (GMP) Guidelines
- USP <1058> – Equipment Qualification
9. SOP Version
Version: 2.0
10. Approval Section
Prepared By | Checked By | Approved By | |
---|---|---|---|
Signature | |||
Date | |||
Name | |||
Designation | |||
Department |
11. Annexures
Annexure 1: Equipment Calibration Log
Equipment ID | Calibration Date | Operator | Calibration Details | Next Calibration Due |
---|---|---|---|---|
Filling Machine 204 | 01/02/2025 | John Doe | Calibration of filling speed and weight | 01/02/2026 |
Annexure 2: Installation Qualification Log
Batch ID | Installation Date | Operator | Installation Parameters | Remarks | |||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Batch 001 |
Batch ID | Installation Date | Operator | Installation Parameters | Remarks |
---|---|---|---|---|
Batch 001 | 02/02/2025 | Jane Smith | Voltage: 220V, Pressure: 3 bars | Installation successful, no issues |
Annexure 3: Installation Qualification Report
Batch ID | Test Date | Test Type | Results | Remarks |
---|---|---|---|---|
Batch 001 | 02/02/2025 | Visual Inspection | Pass | Machine installed correctly, no issues found |
12. Revision History
Revision Date | Revision No. | Revision Details | Reason for Revision | Approved By |
---|---|---|---|---|
01/01/2024 | 1.0 | Initial version of SOP | Creation of SOP for Installation Qualification of capsule filling machines | QA Head |
01/02/2025 | 2.0 | Updated installation procedures and added new testing criteria | Improvement of installation checks and addition of test parameters | QA Head |