Standard Operating Procedure for Operational Qualification (OQ) of Capsule Inspection Machines
Department | Capsule Manufacturing |
---|---|
SOP No. | SOP/CM/167/2025 |
Supersedes | SOP/CM/167/2022 |
Page No. | Page 1 of 8 |
Issue Date | 01/02/2025 |
Effective Date | 05/02/2025 |
Review Date | 01/02/2026 |
1. Purpose
The purpose of this SOP is to outline the Operational Qualification (OQ) process for capsule inspection machines. OQ ensures that the capsule inspection machine operates within specified limits and performs as expected during production. This SOP provides a structured approach to validating the operational functionality of the capsule inspection machine in compliance with GMP and regulatory standards.
2. Scope
This SOP applies to the operational qualification of capsule inspection machines used in the capsule manufacturing process. It covers all aspects of the OQ process, including machine setup, functional tests, and documentation required to ensure the machine meets operational requirements.
3. Responsibilities
- Engineering Team: Responsible for setting up and configuring the capsule inspection machine, performing operational checks, and ensuring that the machine is functioning as per specifications.
- Quality Control (QC) Team: Responsible for performing functional tests on the machine, validating performance, and documenting the results of the OQ process.
- Quality Assurance (QA) Team: Reviews and approves the OQ documentation to ensure compliance with GMP and regulatory standards.
- Production Team: Ensures that the inspection machine is properly integrated into the production line and ready for use after successful OQ completion.
4. Accountability
The Engineering Supervisor is responsible for ensuring that the capsule inspection machine is set up according to the design specifications and is ready for OQ testing. The QA Manager is responsible for reviewing and approving the OQ documentation and ensuring compliance with GMP and regulatory standards. The Production Supervisor ensures the equipment is ready for production after successful completion of the OQ process.
5. Procedure
5.1 Pre-Operational Setup
Before starting the Operational Qualification process, ensure the following preparations are completed:
-
Review OQ Plan
- Review the OQ plan provided by the manufacturer or engineering team. Ensure the plan includes the functional tests, acceptance criteria, and operational parameters to be validated.
-
Prepare Installation Environment
- Ensure the capsule inspection machine is installed and located in the appropriate area of the production line. Verify that the machine is connected to the required utilities (power, compressed air, etc.).
- Verify that the area meets the necessary conditions, including proper lighting and accessibility to operators for safe operation.
-
Calibration and Equipment Checks
- Ensure that the capsule inspection machine is calibrated and functioning as per the design specifications. Record calibration details in the Equipment Calibration Log (Annexure 1).
- Ensure that any ancillary equipment, such as sensors, cameras, and control systems, are operational and calibrated.
5.2 Operational Qualification Process
Follow these steps to conduct the operational qualification of the capsule inspection machine:
-
Verify Functional Components
- Test the basic functional components of the machine, including start/stop buttons, speed control, and emergency stop features. Ensure that all components are responsive and function within specified limits.
-
Verify Operational Parameters
- Test the machine’s operational parameters, including speed, throughput, and accuracy of capsule inspection. Verify that the machine operates within the set limits specified in the OQ plan.
- Ensure that the machine’s capacity (number of capsules per minute) meets the production requirements.
-
Perform Functional Tests
- Run functional tests, such as inspecting capsules for size, shape, color, and defects. Validate the machine’s ability to detect defective capsules and reject them properly.
- Perform tests using different capsule types (e.g., hard gelatin, soft gelatin) to verify that the machine functions as expected across various products.
-
Verify Alarm and Safety Features
- Test the alarm systems to ensure that any faults, such as jammed capsules or machine errors, trigger the appropriate alarms and shutdown procedures.
- Verify that the machine’s safety features, including guards and emergency stops, are functioning correctly.
-
Document OQ Results
- Document the results of all operational tests and verify that all parameters meet the acceptance criteria. Record the results in the OQ Log (Annexure 2).
- If any deviations or failures occur, document them in the OQ report and take corrective actions. Re-test the machine until it meets all operational requirements.
5.3 Post-Qualification Activities
After successful completion of the OQ process, ensure the following tasks are completed:
-
Operator Training
- Train operators on how to use the capsule inspection machine, including basic operations, troubleshooting, and safety procedures.
-
Sign-Off and Approval
- Ensure that the OQ process is completed successfully, and the machine is signed off by the QA Manager for use in production. The OQ Report should be approved and filed for record-keeping.
6. Abbreviations
- SOP: Standard Operating Procedure
- GMP: Good Manufacturing Practice
- OQ: Operational Qualification
- QA: Quality Assurance
- QC: Quality Control
- PPE: Personal Protective Equipment
7. Documents
- Annexure 1: Equipment Calibration Log
- Annexure 2: Operational Qualification Log
- Annexure 3: Operational Qualification Report
8. References
- FDA Guidelines on Equipment Operational Qualification
- Good Manufacturing Practice (GMP) Guidelines
- USP <1058> – Equipment Qualification
9. SOP Version
Version: 2.0
10. Approval Section
Prepared By | Checked By | Approved By | |
---|---|---|---|
Signature | |||
Date | |||
Name | |||
Designation | |||
Department |
11. Annexures
Annexure 1: Equipment Calibration Log
Equipment ID | Calibration Date | Operator | Calibration Details | Next Calibration Due |
---|---|---|---|---|
Inspection Machine 300 | 01/02/2025 | John Doe | Calibration of camera focus and capsule detection sensors | 01/02/2026 |
Annexure 2: Operational Qualification Log
Batch ID | OQ Date | Operator | Test Type | Results |
---|---|---|---|---|
Batch 001 | 02/02/2025 | Jane Smith | Visual Inspection Test | Pass |
Annexure 3: Operational Qualification Report
Batch ID | Test Date | Test Type | Results | Remarks |
---|---|---|---|---|
Batch 001 | 02/02/2025 | Functionality Test | Pass | Machine operates within expected parameters |
12. Revision History
Revision Date | Revision No. | Revision Details | Reason for Revision | Approved By |
---|---|---|---|---|
01/01/2024 | 1.0 | Initial version of SOP | Creation of SOP for operational qualification of capsule inspection machines | QA Head |
01/02/2025 | 2.0 | Updated operational checks and added new acceptance criteria for machine functionality | Improvement of operational qualification tests and incorporation of updated requirements | QA Head |