1. Purpose
This Standard Operating Procedure (SOP) establishes the guidelines for systematic documentation and record-keeping of all raw materials received at the facility. Proper documentation ensures traceability, accountability, and compliance with Good Manufacturing Practices (GMP) and regulatory requirements. This SOP outlines:
- Procedures for accurate recording of raw material receipt, inspection, and approval processes.
- Maintenance of documentation for audit readiness and regulatory compliance.
- Storage, retrieval, and control of raw material records to ensure data integrity and security.
- Roles and responsibilities of personnel in managing documentation for raw material receipt.
2. Scope
This SOP applies to all departments involved in the receipt and handling of raw materials, including the Warehouse, Quality Assurance (QA), Quality Control (QC), and Procurement. It covers:
- Documentation requirements for receiving, inspecting, and releasing raw materials.
- Record-keeping of supplier documentation, Certificates of Analysis (CoAs), and regulatory certificates.
- Procedures for managing deviations, non-conformances, and corrective actions related to raw materials.
- Retention and archiving of records in compliance with regulatory standards.
3. Responsibilities
-
Warehouse Personnel:
- Ensure accurate documentation of raw material receipts, including supplier information, batch numbers, and inspection results.
- Maintain the Raw Material Receiving Register and ensure timely updates with relevant data.
- Ensure that all documentation is complete, legible, and free from unauthorized alterations.
-
Quality Assurance (QA) Team:
- Review and verify the completeness and accuracy of raw material documentation.
- Ensure compliance with GMP and regulatory requirements for record-keeping.
- Oversee the archiving and retrieval of raw material records and ensure proper retention periods are followed.
-
Quality Control (QC) Team:
- Document sampling and testing results for raw materials in accordance with SOPs.
- Ensure test reports, CoAs, and analytical data are properly stored and accessible for review.
-
Procurement Department:
- Maintain supplier-related documentation, including purchase orders, invoices, and compliance certificates.
- Coordinate with suppliers to obtain missing or incomplete documentation.
4. Accountability
The Warehouse Manager is responsible for ensuring accurate documentation of raw material receipts. The QA Manager holds the authority to approve documentation processes and ensure compliance with GMP and regulatory requirements. Any deviations from this SOP must be documented and approved by QA to maintain compliance.
5. Procedure
5.1 Pre-Receipt Documentation
-
Review of Purchase Orders and Supplier Documentation
- Procurement provides the Warehouse with the purchase order (PO) and supplier documentation, including invoices, packing lists, and Certificates of Analysis (CoAs).
- Ensure that all supplier documentation is complete and matches the PO details, including material name, quantity, and batch number.
-
Preparation of Raw Material Receiving Register
- Ensure that the Raw Material Receiving Register (Annexure-1) is updated and ready for recording incoming materials.
- Prepare any additional forms required for documenting inspections and QC testing.
5.2 Receiving and Documentation
-
Recording Receipt Details
- Upon receipt of raw materials, Warehouse personnel record the following details in the Raw Material Receiving Register:
- Date of receipt.
- Supplier name and contact information.
- Material name, batch number, and quantity received.
- Purchase order (PO) number and invoice number.
- Ensure that all entries are legible, complete, and made using permanent ink.
- Upon receipt of raw materials, Warehouse personnel record the following details in the Raw Material Receiving Register:
-
Documentation of Inspection Results
- Record inspection findings, including packaging integrity, labeling accuracy, and any discrepancies observed during visual checks.
- Indicate whether the materials were accepted, quarantined, or rejected based on the inspection results.
5.3 Quality Assurance Review
-
Verification of Documentation
- QA reviews the Raw Material Receiving Register and associated documentation to ensure accuracy and completeness.
- Cross-verify supplier CoAs, compliance certificates, and any regulatory documentation provided with the shipment.
-
Approval and Filing of Documentation
- Once verified, QA approves the documentation and ensures it is properly filed and stored in the raw material documentation archive.
- Ensure that electronic records, if maintained, are backed up and secured in compliance with data integrity standards.
5.4 Record Retention and Archiving
-
Retention Periods
- Maintain raw material documentation for a minimum of five years or as specified by regulatory guidelines.
- Ensure that records related to critical materials or long-term stability studies are retained for extended periods as required.
-
Archiving Procedures
- Store physical records in a secure, fireproof, and humidity-controlled environment.
- Ensure that electronic records are stored on secure servers with appropriate access controls and regular backups.
- Label archived records clearly with reference numbers for easy retrieval during audits or inspections.
5.5 Handling Deviations and Non-Conformances
-
Documentation of Deviations
- Record any deviations or non-conformances related to raw material receipt in the Deviation Report Form.
- Include details such as the nature of the deviation, corrective actions taken, and the responsible personnel involved.
-
Review and Approval of Deviations
- QA reviews all deviation reports and ensures that appropriate corrective and preventive actions (CAPAs) are implemented.
- Maintain a log of all deviations and ensure that they are readily accessible for review during audits.
6. Abbreviations
- SOP: Standard Operating Procedure
- GMP: Good Manufacturing Practice
- QA: Quality Assurance
- QC: Quality Control
- PO: Purchase Order
- CoA: Certificate of Analysis
- CAPA: Corrective and Preventive Action
7. Documents
- Raw Material Receiving Register (Annexure-1)
- Sampling Log (Annexure-2)
- Purchase Orders (PO), Invoices, and Packing Lists
- Certificates of Analysis (CoAs) and Compliance Certificates
- Deviation Reports and Non-Conformance Logs
8. References
- 21 CFR Part 211 – Current GMP for Finished Pharmaceuticals (US FDA)
- EU GMP Guidelines Part I – Basic Requirements for Medicinal Products
- ICH Q7 – GMP for Active Pharmaceutical Ingredients
- Company-Specific Procurement, QA, and Warehouse Policies
9. SOP Version
Version: 2.0
10. Approval Section
Prepared By | Checked By | Approved By | |
---|---|---|---|
Signature | |||
Date | |||
Name | |||
Designation | |||
Department |
11. Annexures
Annexure-1: Raw Material Receiving Register
Date | Supplier Name | Material Name | Batch Number | PO Number | Quantity | Inspection Findings | Remarks |
---|---|---|---|---|---|---|---|
01/02/2025 | ABC Chemicals | API-X | X-2025-001 | PO-12345 | 100 kg | Packaging Intact, CoA Verified | Accepted |
02/02/2025 | XYZ Pharma | Excipient-Y | Y-2025-002 | PO-67890 | 200 kg | Labeling Discrepancy Found | Quarantined, Pending QA Review |
Annexure-2: Sampling Log
Date | Material Name | Batch Number | Sampling Personnel | QC Test Performed | Result | Remarks |
---|---|---|---|---|---|---|
01/02/2025 | API-X | X-2025-001 | John Doe | Identity Test | Pass | Approved for Use |
03/02/2025 | Excipient-Y | Y-2025-002 | Jane Smith | Purity Test | Fail | Rejected Due to Labeling Error |
Revision History:
Revision Date | Revision No. | Revision Details | Reason for Revision | Approved By | Page No. | Ref. Point No. | Details of Revision |
---|---|---|---|---|---|---|---|
01/01/2024 | 1.0 | Initial Version | New SOP Creation | QA Head | All | All | Established documentation procedures for raw material receipt. |
01/02/2025 | 2.0 | Enhanced Record-Keeping and Archiving Procedures | Standardization of Document | QA Head | All | All | Added retention periods and electronic record management guidelines. |